PMP-KR 문제 51
The project manager should call a stakeholder meeting along with team members and seek consensus about the design features. This is because the project manager needs to resolve the conflict among the team members and ensure that the design meets the stakeholder expectations and requirements. The project manager should use conflict resolution techniques such as collaborating, compromising, or problem-solving to facilitate a constructive dialogue and reach a mutually acceptable agreement. The project manager should also consider the impact of the design features on the project scope, quality, schedule, and cost and communicate any changes or issues to the relevant stakeholders.
Option A is not a good action, as asking the project sponsor to make the decision about the design features may not be appropriate or effective. It may also undermine the team members' autonomy, creativity, and ownership of their work. The project manager should try to involve the team members and other stakeholders in the decision-making process and not rely on the project sponsor's authority or influence.
Option C is not a good action, as asking stakeholders to reduce the scope in order to meet project deadlines may not be feasible or desirable. It may also create dissatisfaction, confusion, and resistance among the stakeholders. The project manager should try to deliver the project scope as agreed and not change it without proper justification and approval.
Option D is not a good action, as reviewing the design with the team members and proposing a new launch date may not be necessary or beneficial. It may also create additional risks, issues, and delays for the project. The project manager should try to launch the project as planned and not postpone it without proper justification and approval. References:
[PMBOK Guide], 6th edition, page 386, section 10.3
[PMP Exam Content Outline], page 12, task 4 under domain 3
PMP-KR 문제 52
= The project manager should use iterative life cycles involving stakeholders to ensure that the needs of stakeholders are consistently met. This is the best way to cope with the rapidly changing business environment and to deliver value incrementally. By involving stakeholders in each iteration, the project manager can obtain their feedback, validate their requirements, and incorporate their changes. This also helps to improve the stakeholder satisfaction and engagement, and to reduce the risks and uncertainties. The other options are not the best actions to take in this situation, as they do not address the dynamic nature of the project or the stakeholder needs. References: = A Guide to the Project Management Body of Knowledge (PMBOK Guide)
- Seventh Edition, Chapter 1: Introduction, Section 1.4: Project Life Cycle, Page 19-20.
PMP-KR 문제 53
어떤 프로젝트 접근 방식이 시나리오에 적합합니까?
According to the PMBOK Guide, a project approach is the way a project is planned, executed, monitored, controlled, and closed. A project approach should be designed based on the context of the project, its objectives, stakeholders, governance, and the environment1. A project approach should use "just enough" process to achieve thedesired outcome while maximizing value, managing cost, and enhancing speed1. A project approach can be predictive, agile, or hybrid, depending on the degree of uncertainty and change involved in the project2.
In this scenario, the project is in a very initial stage and the requirements are evolving, which means there is a high level of uncertainty and change. The customer would like to launch the product keeping the scope flexible, which means they are open to feedback and adaptation. The project team intends to start the work based on the forecast of a similar project delivered last year, which means they have some historical data and experience to guide them. These factors suggest that an agile approach would be suitable for this project, as it can provide flexibility, adaptability, and customer focus while delivering value incrementally and iteratively2.
One of the most popular agile approaches is Scrum, which is a framework for managing complex projects that deliver products or services in short iterations called sprints3. Scrum involves a self-organizing and cross-functional team, a product owner who represents the customer and defines the product backlog, and a Scrum master who facilitates the Scrum process and removes impediments3. Scrum also involves several events, such as sprint planning, daily Scrum, sprint review, and sprint retrospective, to ensure collaboration, communication, and continuous improvement3.
Therefore, executing the project as a Scrum project would suit the scenario, as it can accommodate the evolving requirements, the flexible scope, and the competitive market. Scrum can also leverage the forecast of the similar project as an input for the product backlog and the sprint planning, and adjust the work based on the feedback and the changes in the environment.
References: 1: 12 Principles of Project Management 2: Project Management Professional (PMP) Certification 3: PMP Certification Info Summary
PMP-KR 문제 54
프로젝트 관리자는 무엇을 해야 합니까?
According to the Agile Practice Guide, a hybrid project is a project that combines elements of predictive and adaptive project management methodologies. A hybrid project may use different methodologies for different phases or deliverables of the project, or it may blend the practices and techniques of different methodologies within the same phase or deliverable. A hybrid project may also use different tools and techniques to support the project management and delivery, such as software applications, templates, documents, or artifacts. In this scenario, the project manager is managing a hybrid project that uses software to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the latest project schedule. This is a communication issue that may affect the stakeholder engagement and satisfaction, as well as the project performance and delivery. The best course of action is to make sure all stakeholders have access to the system and know where to find project artifacts. This can help the project manager to ensure that the project communication is consistent, clear, and effective, and that the stakeholders are kept informed and updated on the project progress and status. Making sure all stakeholders have access to the system and know where to find project artifacts (option B) is the best solution to the issue, as it demonstratesproactive and respectful project communication and stakeholder management. Sending the project schedule via email to the stakeholders who need that information (option A) may not be sufficient or efficient, as it may create inconsistency and confusion among the stakeholders, and may increase the workload and overhead of the project manager. Escalating the issue to the steering committee and asking them to deal with the stakeholders' lack of training (option C) may also be unnecessary or inappropriate, as it may imply that the project manager is unable to handle the issue and may damage the trust and relationship with the stakeholders. Advising the project management office (PMO) that there is a resource gap for sharing project artifacts effectively (option D) may also be unrealistic or irrelevant, as it may not address the root cause of the issue or provide a clear guidance on how to improve the project communication or stakeholder engagement. References: : Project Management Institute. (2017). Agile Practice Guide. Newtown Square, PA: Author1 : Ultimate Guide To Hybrid Project Methodologies & How To Make Them 2 : A Little Bit of Both - Project Management Institute 3
PMP-KR 문제 55
상황을 개선하기 위해 프로젝트 관리자는 무엇을 해야 합니까?
According to the PMBOK Guide, 6th edition, page 349, the project manager is responsible for managing the project team and ensuring a positive team environment. One of the tools and techniques for managing the project team is conflict management, which involves identifying, addressing, and resolving conflicts among the project team members and other stakeholders. The project manager should use a collaborative or problem-solving approach to conflict management, which involves discussing the issues openly, listening to different perspectives, and finding a mutually acceptable solution that satisfies the needs and interests of all parties involved. By discussing the team members' concern with the construction manager and seeking solutions, the project manager can help to resolve the cultural differences, improve the communication and cooperation, and enhance the team performance and morale. References:
PMBOK Guide, 6th edition, page 349
Free PMP Practice Exam Questions - 120 Sample Test Questions
- 다른 버전
- 817PMI.PMP-KR.v2026-08-27.q1110
- 5316PMI.PMP-KR.v2026-08-21.q86
- 1370PMI.PMP-KR.v2026-08-21.q927
- 8130PMI.PMP-KR.v2026-06-01.q1069
- 6326PMI.PMP-KR.v2026-05-07.q925
- 1720PMI.PMP-KR.v2026-03-28.q242
- 5029PMI.PMP-KR.v2026-03-27.q939
- 5525PMI.PMP-KR.v2026-03-09.q911
- 5322PMI.PMP-KR.v2026-03-07.q681
- 5928PMI.PMP-KR.v2026-03-05.q857
- 3289PMI.PMP-KR.v2026-03-04.q280
- 5728PMI.PMP-KR.v2025-03-29.q751
- 5598PMI.PMP-KR.v2024-02-27.q469
- 3732PMI.PMP-KR.v2023-12-04.q235
- 1555PMI.PMP-KR.v2023-10-19.q177
- 2634PMI.PMP-KR.v2023-05-15.q244
- 최근 업로드
- 134Oracle.1Z1-171.v2026-09-06.q38
- 151SAP.C_S4TM.v2026-09-06.q71
- 161Oracle.1Z0-1054-26.v2026-09-06.q65
- 193Huawei.H12-831_V1.0.v2026-09-06.q231
- 136Salesforce.Plat-Arch-205.v2026-09-06.q28
- 151Salesforce.Plat-Arch-203.v2026-09-06.q90
- 142Oracle.1Z0-1050-26.v2026-09-05.q19
- 214Salesforce.Manufacturing-Cloud-Professional.v2026-09-05.q111
- 231EXIN.ITILFND_V4.v2026-09-05.q129
- 251Citrix.1Y0-312.v2026-09-05.q182
PDF 파일 다운로드
메일 주소를 입력하시고 다운로드 하세요. PMI.PMP-KR.v2024-02-10.q164 모의시험 시험자료를 다운 받으세요.