PMP-KR 문제 66
완료 날짜가 영향을 받지 않도록 프로젝트 관리자는 프로젝트를 어떻게 압축해야 합니까?
The project manager should fast-track the project to compress the project schedule and ensure the completion date is not affected by the unforeseen risk occurrence. Fast-tracking is a schedule compression technique that involves performing activities in parallel that were originally planned to be performed sequentially1. This can reduce the overall duration of the project, but it may also increase the risk and complexity of the project.
Reducing the project scope (A) may not be possible or acceptable, as it may affect the project deliverables and customer satisfaction. Increasing the project cost (B) may not be feasible or beneficial, as it may not guarantee the reduction of the project duration. Adding more project resources may not be available or effective, as it may introduce new challenges such as coordination, communication, and training. References: 1: PMBOK Guide, 6th Edition, p. 215.
PMP-KR 문제 67
프로젝트 관리자는 어떤 두 가지 조치를 취해야 합니까? (2개 선택)
= According to the PMBOK Guide, 7th edition, the project manager should select the appropriate delivery approach for the project based on the project characteristics, stakeholder needs, and organizational context1. The project manager should also facilitate the team's transition to the chosen delivery approach by providing guidance, coaching, and support2. Therefore, the project manager should brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team (option D). This can help the project manager to tailor the agile approach to the project's needs and constraints, and to address the team's concerns and expectations. The project manager should also conduct training sessions with the team so that the team can understand what the agile approach and mindset are (option E). This can help the team to learn the principles, values, and practices of agile, and to develop the skills and competencies required for agile delivery3. Interviewing the most resistant team members to persuade them to try to accept an agile approach (option A) may not be effective, as it may create more resistance and resentment among the team members. The project manager should instead involve the whole team in the decision-making process and seek their feedback and input. Meeting with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile (option B) may not be helpful, as it may undermine the team's autonomy and motivation. The project manager should instead communicate with management the benefits and challenges of the agile approach, and seek their support and sponsorship. Asking the team to identify the product backlog and create a kanban board for the team to manage and follow the approach (option C) may not be appropriate, as it may be too premature and prescriptive. The project manager should first ensure that the team understands the rationale and the basics of the agile approach, and then collaboratively define the project scope and the workflow with the team. References: 1: PMBOK Guide, 7th edition, page 37 2: PMBOK Guide, 7th edition, page 38 3: PMBOK Guide, 7th edition, page 39 : PMBOK Guide, 7th edition, page 40
PMP-KR 문제 68
프로젝트 범위가 완전히 정의되었는지 확인하기 위해 프로젝트 관리자는 무엇을 해야 합니까?
The project manager should help the sponsors and stakeholders create a clear and shared product vision that describes the purpose, features, and benefits of the product. The product vision guides the project scope and provides a common understanding of what the project aims to deliver. The project manager should also facilitate collaboration and communication between the team and the product owner, who is responsible fordefining and prioritizing the product requirements. The team and the product owner should work together to refine and validate the requirements throughout the project, using feedback loops and iterative delivery. This way, the project scope is continuously aligned with the customer needs and expectations, and any changes or uncertainties are managed effectively. References: (Project Management Professional (PMP) Reference Materials source and documents) A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter
2: Value Delivery System, Section 2.3.1: Agile Principles and Values
Agile Practice Guide, Chapter 3: Life Cycle Selection, Section 3.1: Introduction to Life Cycles
[PMP Exam Content Outline], Domain II: Process, Task 2: Determine project scope.
PMP-KR 문제 69
이 상황에서 프로젝트 관리자는 무엇을 해야 합니까?
In an agile team, the project manager should foster a culture of self-organization and empowerment, where the team members are given the authority and responsibility to make decisions that affect their work. This can increase the team's motivation, creativity, and productivity, as well as reduce the need for micromanagement and bureaucracy. Discouraging the team members from asking for more autonomy, or delegating the decision-making to the team lead or the management team, can undermine the agile principles and values, and create dissatisfaction, confusion, or conflict among the team members. References: (Project Management Professional (PMP) Reference Materials source and documents) A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter
2: Value Delivery System, Section 2.3.1: Agile Principles and Values
Agile Practice Guide, Chapter 2: An Agile Mindset, Section 2.2: Empowerment and Collaboration
[PMP Exam Content Outline], Domain III: People, Task 8: Support team performance.
PMP-KR 문제 70
향후 이러한 상황을 방지하기 위해 프로젝트 관리자는 다음 중 어떤 조치를 취해야 합니까?
this question is related to the Project Management Professional (PMP) certification exam, which is a credential that validates the knowledge and skills of project managers. The PMP exam is based on the PMBOK Guide,
7th edition, which is a standard that provides a framework and best practices for managing projects. The question describes a situation where at a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week, the project team realizes that the activities were executed in the wrong way because each team member had a different understanding. These misunderstandings have caused a delay in the project. The question asks which of the following actions should the project manager take to avoid this situation in the future.
Based on this information, the best answer is option D, which is to document the agreement in the meeting minutes. This is because documenting the agreement in the meeting minutes is a communication management practice that can help the project manager to ensure that the project team has a clear and consistent understanding of the project activities and expectations. Meeting minutes are documents that record the key information and decisions from a meeting, such as the date, time, location, attendees, agenda, action items, and follow-up actions. Documenting the agreement in the meeting minutes can help the project manager to communicate and confirm the project activities and expectations with the project team, as well as to monitor and control the project progress and performance. Documenting the agreement in the meeting minutes can help the project manager to avoid the situation of executing the activities in the wrong way, as well as to prevent or reduce the project delays.
Option A, which is to conduct reviews prior to performing activities, is not a good answer. This is because conducting reviews prior to performing activities may not be relevant or effective to avoid the situation in the future. Reviews are processes that involve examining and evaluating the project work or deliverables to ensure that they meet the quality standards and requirements. Reviews may include techniques such as inspections, audits, walkthroughs, or peer reviews. Conducting reviews prior to performing activities can help the project manager to identify and correct any errors or defects in the project work or deliverables, as well as to improve the quality and value of the project. However, conducting reviews prior to performing activities may not help the project manager to avoid the situation of executing the activities in the wrong way, as it may not address the issue of unclear or inconsistent understanding of the project activities and expectations among the project team.
Option B, which is to use a common communication terminology, is not a good answer. This is because using a common communication terminology may not be enough or sufficient to avoid the situation in the future.
Communication terminology is a set ofwords or phrases that are used to convey information or messages in a specific context or domain. Communication terminology may include acronyms, abbreviations, jargon, or slang. Using a common communication terminology can help the project manager to facilitate clear and consistent communication and understanding among the project team and other stakeholders, as well as to avoid or reduce any confusion or ambiguity. However, using a common communication terminology may not help the project manager to avoid the situation of executing the activities in the wrong way, as it may not ensure that the project team has a complete and accurate understanding of the project activities and expectations.
Option C, which is to monitor the team's performance metrics, is not a good answer. This is because monitoring the team's performance metrics may not be relevant or effective to avoid the situation in the future.
Performance metrics are measures that indicate the progress and performance of the project team or the project work. Performance metrics may include indicators such as schedule variance, cost variance, quality metrics, customer satisfaction, or team engagement. Monitoring the team's performance metrics can help the project manager to track and evaluate the project team's performance and productivity, as well as to identify and address any issues or risks that may affect the project outcomes. However, monitoring the team's performance metrics may not help the project manager to avoid the situation of executing the activities in the wrong way, as it may not prevent or resolve the issue of unclear or inconsistent understanding of the project activities and expectations among the project team. References: PMBOK Guide, 7th edition; PMP Exam Content Outline; PMP Sample Test Questions.
- 다른 버전
- 941PMI.PMP-KR.v2026-08-27.q1110
- 5326PMI.PMP-KR.v2026-08-21.q86
- 1417PMI.PMP-KR.v2026-08-21.q927
- 8226PMI.PMP-KR.v2026-06-01.q1069
- 6371PMI.PMP-KR.v2026-05-07.q925
- 1731PMI.PMP-KR.v2026-03-28.q242
- 5054PMI.PMP-KR.v2026-03-27.q939
- 5598PMI.PMP-KR.v2026-03-09.q911
- 5360PMI.PMP-KR.v2026-03-07.q681
- 6002PMI.PMP-KR.v2026-03-05.q857
- 3318PMI.PMP-KR.v2026-03-04.q280
- 5766PMI.PMP-KR.v2025-03-29.q751
- 5636PMI.PMP-KR.v2024-02-27.q469
- 3739PMI.PMP-KR.v2023-12-04.q235
- 1575PMI.PMP-KR.v2023-10-19.q177
- 2639PMI.PMP-KR.v2023-05-15.q244
- 최근 업로드
- 135Saviynt.SCAIP.v2026-09-07.q20
- 294ISC.CCSP-KR.v2026-09-07.q424
- 137Oracle.1Z0-1032-26.v2026-09-07.q23
- 159Nursing.PMHN-BC.v2026-09-07.q38
- 220Cisco.300-430.v2026-09-07.q266
- 194Oracle.1Z1-171.v2026-09-06.q38
- 200SAP.C_S4TM.v2026-09-06.q71
- 194Oracle.1Z0-1054-26.v2026-09-06.q65
- 261Huawei.H12-831_V1.0.v2026-09-06.q231
- 164Salesforce.Plat-Arch-205.v2026-09-06.q28
PDF 파일 다운로드
메일 주소를 입력하시고 다운로드 하세요. PMI.PMP-KR.v2024-02-10.q164 모의시험 시험자료를 다운 받으세요.
