PMP-KR 문제 141
According to the PMBOK Guide, 7th edition, communication management is the process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information. Communication management involves planning, managing, and monitoring communications throughout the project life cycle. Communication management also involves considering the communication needs, preferences, and cultural differences of the project stakeholders. In this question, the project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference. The question asks what the project manager can do to improve interactions between the team members in both countries.
Based on this information, the best answer is option C, which is to identify virtual communication methods and arrange for regular team meetings accordingly. This is because identifying virtual communication methods and arranging for regular team meetings is a communication management practice that can help the project manager to facilitate effective and efficient communication and collaboration among geographically dispersed team members. Virtual communication methods are tools and techniques that enable remote communication and interaction, such as email, phone, video conferencing, instant messaging, online forums, and social media.
Regular team meetings are sessions that allow the team members to share information, provide updates, resolve issues, make decisions, and give feedback. Identifying virtual communication methods and arranging for regular team meetings can help the project manager to overcome the challenges posed by the time difference, as well as to build trust, rapport, and teamwork among the team members in both countries.
Option A, which is to ensure full participation of both the product owner and business SMEs in scope planning sessions, is not a good answer. This is because ensuring full participation of both the product owner and business SMEs in scope planning sessions may not be relevant or sufficient to improve interactions between the team members in both countries. Scope planning sessions are sessions that involve defining and documenting the project scope, deliverables, assumptions, and constraints. Scope planning sessions may not require the participation of all team members, as some team members may not be involved in the scope definition or validation. Scope planningsessions may not address the communication and collaboration issues that may arise from the time difference, as they may not occur frequently or regularly.
Option B, which is to explore the opportunity to have both teams colocated, is not a good answer. This is because exploring the opportunity to have both teams colocated may not be feasible or cost-effective, as it may involve additional expenses, logistics, and risks. Colocating both teams may also disrupt their work environment, productivity, and motivation. Colocating both teams may not be necessary, as virtual communication methods and regular team meetings can provide a similar level of interaction and collaboration.
Option D, which is to plan for frequent face-to-face meetings, is not a good answer. This is because planning for frequent face-to-face meetings may not be possible or practical, as it may involve travel, time, and budget constraints. Face-to-face meetings may also expose the team members to health and safety risks, especially during the COVID-19 pandemic. Face-to-face meetings may not be preferable, as some team members may prefer virtual communication methods or have personal or professional commitments that prevent them from traveling. Face-to-face meetings may not be superior, as virtual communication methods and regular team meetings can offer comparable benefits and outcomes. References: PMBOK Guide, 7th edition, Chapter 8:
Communication1; PMI, 2023, PMP Exam Content Outline, Domain II: Process, Task 10: Plan and manage project/phase communications.
PMP-KR 문제 142
프로젝트 관리자가 취해야 할 두 가지 조치는 무엇입니까? (2개를 선택하세요.)
= The project manager should take a proactive and collaborative approach to deal with the neighborhood resistance, which is a potential risk to the project. The project manager should analyze the situation and find out the root cause of the negative attitude, such as noise, pollution, traffic, safety, or other concerns. The project manager should also set up a meeting with the neighborhood representatives to win their cooperation and support, by addressing their issues, providing information, offering benefits, or negotiating solutions.
Asking the customer to extend the deadline, asking the mayor to intervene, or sending letters to the neighbors are not effective actions, as they may escalate the conflict, damage the relationship, or ignore the problem.
References:
PMBOK Guide 7th Edition, Chapter 8: Stakeholder Performance, Section 8.2: Engage Stakeholders, Page 205 PMBOK Guide 6th Edition, Chapter 13: Stakeholder Management, Section 13.3: Manage Stakeholder Engagement, Page 523 Agile Practice Guide, Chapter 3: Implementing Agile: Creating an Agile Environment, Section 3.3:
Customer Engagement Practices, Page 37
PMP-KR 문제 143
프로젝트 관리자는 무엇을 해야 합니까?
A hybrid approach is a combination of predictive and adaptive methods that are tailored to suit the specific needs and characteristics of a project. A hybrid approach can offer the benefits of both flexibility and predictability, as well as the ability to adapt to changing requirements and deliver value incrementally.
However, a hybrid approach also requires a careful analysis of the project context, the interdependencies of the processes, and the alignment of the stakeholders. Therefore, if the project manager observes lower velocity and a high volume of tasks in the testing queue, the best option is to work with the team to understand and solve the issues. The project manager should collaborate with the team to identify the root causes of the testing backlog, such as unclear requirements, inadequate testing tools, insufficient testing skills, or poor communication. The project manager should also facilitate the team to find the best solutions, such as reprioritizing the backlog, adjusting the testing strategy, improving the testing environment, or seeking feedback from the stakeholders. The project manager should also monitor and control the testing process and the project performance, as well as communicate the progress and the issues to the relevant stakeholders. The other options are not as suitable or effective for addressing the testing backlog, as they may not follow the established guidelines or consider the impact of the changes on the project objectives and constraints. Adding a new resource with testing skills to the team may not be realistic or feasible, as it may increase the cost, risk, or complexity of the project, or it may disrupt the team dynamics or the sprint rhythm. Providing testing training to all the project team members may not be necessary or beneficial, as it may consume time, resources, or budget that could be used for other project activities, or it may not improve the testing quality or efficiency significantly. Increasing the sprint duration so the testing can be completed may not be optimal or timely, as it may delay the delivery of value to the stakeholders, or it may affect the scope, schedule, or quality of the project. References:
PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, Project Management Institute Inc., 2017, pp. 28-29, 35-36, 54-55, 487.
Ultimate Guide To Hybrid Project Methodologies & How To Make Them, The Digital Project Manager,
2023, pp. 4-5, 9-10.
A Guide to Hybrid Project Management: Blending Agile and Traditional PM, Float, 2023, pp. 3-4, 7-8.
PMP-KR 문제 144
프로젝트 관리자는 무엇을 해야 합니까?
According to the PMBOK Guide, 7th edition, one of the key principles for project delivery is to "embrace uncertainty and respond to change" (p. 12). This principle implies that the project manager should help the team identify and address risks and issues as they arise, rather than relying on predefined plans or reserves.
The project manager should help the team review the project approach to initiate the corrective actions, as this will help to resolve the issue, learn from the experience, and improve the project outcomes. Asking the sponsor to approve an additional iteration, asking the sponsor for money, or asking the team to include the contingency plan in the backlog are not effective ways to handle the situation, as they do not address the root cause of the problem, which is the unidentified risk that became an issue. References: PMBOK Guide, 7th edition, p. 12; PMP Exam Content Outline, Domain III: Business Environment, Task 3.
Learn more
1blob:https://www.bing.com/84891d16-e812-4707-98e3-ce75ceb5332byoutube.com2blob:https://www.bing.com
PMP-KR 문제 145
= The project manager should adjust their responsibilities accordingly by becoming a servant leader by supporting team collaboration and removing impediments when implementing a hybrid approach that will replace a predictive approach on an upcoming project. According to the PMBOK Guide, a hybrid approach is a project management approach that combines predictive and adaptive (agile) practices to fit the project context, complexity, and uncertainty[1]. A hybrid approach requires the project manager to balance the need for planning and control with the need for flexibility and responsiveness to changing customer needs and expectations[1]. Therefore, the project manager should adopt a servant leadership style, which is a leadership style that focuses on empowering and serving the team rather than directing and controlling them[1]. A servant leader supports team collaboration by facilitating communication, feedback, and decision making among the team members and other stakeholders[1]. A servant leader also removes impediments by identifying and resolving issues that prevent the team from delivering value to the customer[1]. By becoming a servant leader, the project manager can enhance the team performance and satisfaction, and deliver customer value in a hybrid approach. The other options are not appropriate for this situation, as they do not reflect the role of the project manager in a hybrid approach.
Introducing new communication tools to the project team members is a possible action that the project manager can take, but it is not the main responsibility of the project manager in a hybrid approach.
Communication tools are only effective if they are used to support team collaboration and customer feedback, which are the core values of a hybrid approach[1].
Requesting a scrum master to focus on the collaboration while the project manager focuses on the coordination is a wrong way to implement a hybrid approach, as it creates a role conflict and a lack of alignment between the project manager and the scrum master. A scrum master is a role in an agile framework that coaches and guides the team and the product owner in applying agile principles and practices[1]. Ascrum master is not a substitute for the project manager, nor is the project manager a superior to the scrum master. In a hybrid approach, the project manager and the scrum master should work together to ensure the project objectives and customer expectations are met, and to share the responsibilities of collaboration and coordination[1].
Delegating coordination activities to the product owner so the project manager can focus on managing collaboration is a wrong way to implement a hybrid approach, as it creates a role overload and a lack of accountability for the product owner. A product owner is a role in an agile framework that represents the voice of the customer and defines and prioritizes the product backlog[1]. A product owner is not responsible for coordinating the project activities, resources, and stakeholders, which are the primary functions of the project manager. In a hybrid approach, the project manager and the product owner should work together to ensure the product vision and scope are aligned with the project goals and constraints, and to share the responsibilities of collaboration and coordination[1].
References: [1]: PMBOK Guide, 7th edition, pages 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28,
29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51, 52, 53...
- 다른 버전
- 815PMI.PMP-KR.v2026-08-27.q1110
- 5316PMI.PMP-KR.v2026-08-21.q86
- 1370PMI.PMP-KR.v2026-08-21.q927
- 8129PMI.PMP-KR.v2026-06-01.q1069
- 6326PMI.PMP-KR.v2026-05-07.q925
- 1720PMI.PMP-KR.v2026-03-28.q242
- 5029PMI.PMP-KR.v2026-03-27.q939
- 5525PMI.PMP-KR.v2026-03-09.q911
- 5322PMI.PMP-KR.v2026-03-07.q681
- 5927PMI.PMP-KR.v2026-03-05.q857
- 3287PMI.PMP-KR.v2026-03-04.q280
- 5728PMI.PMP-KR.v2025-03-29.q751
- 5598PMI.PMP-KR.v2024-02-27.q469
- 3732PMI.PMP-KR.v2023-12-04.q235
- 1555PMI.PMP-KR.v2023-10-19.q177
- 2634PMI.PMP-KR.v2023-05-15.q244
- 최근 업로드
- 134Oracle.1Z1-171.v2026-09-06.q38
- 151SAP.C_S4TM.v2026-09-06.q71
- 161Oracle.1Z0-1054-26.v2026-09-06.q65
- 192Huawei.H12-831_V1.0.v2026-09-06.q231
- 135Salesforce.Plat-Arch-205.v2026-09-06.q28
- 151Salesforce.Plat-Arch-203.v2026-09-06.q90
- 142Oracle.1Z0-1050-26.v2026-09-05.q19
- 214Salesforce.Manufacturing-Cloud-Professional.v2026-09-05.q111
- 231EXIN.ITILFND_V4.v2026-09-05.q129
- 251Citrix.1Y0-312.v2026-09-05.q182
PDF 파일 다운로드
메일 주소를 입력하시고 다운로드 하세요. PMI.PMP-KR.v2024-02-10.q164 모의시험 시험자료를 다운 받으세요.