SMC 문제 21
Which of the following statements about Release Planning Session is/are Correct?
A) Release Planning Sessions are conducted to develop a plan that defines when various sets of usable functionality or products will be delivered to the customer.
B) Release Planning Sessions enable the Scrum Team to have an overview of the releases and delivery schedule for the product they are developing.
C) Whether the releases will follow a phased deployment pattern or a continuous deployment pattern depends on the stakeholder requirements.
D) Release Planning Sessions should produce a detailed Release Plan for the entire project.
A) Release Planning Sessions are conducted to develop a plan that defines when various sets of usable functionality or products will be delivered to the customer.
B) Release Planning Sessions enable the Scrum Team to have an overview of the releases and delivery schedule for the product they are developing.
C) Whether the releases will follow a phased deployment pattern or a continuous deployment pattern depends on the stakeholder requirements.
D) Release Planning Sessions should produce a detailed Release Plan for the entire project.
SMC 문제 22
You are the Scrum Master of a project to construct an IT Tech Park. This project requires adhering to stringent quality standards at every stage of development. A Scrum Core Team is formed for this project in which the Scrum Master is supposed to facilitate a "team first" mentality when it comes to quality. You must ensure all of the following to maintain quality in Scrum, EXCEPT:
SMC 문제 23
At the end of each Sprint the Scrumboard is _________.
SMC 문제 24
Gary, a Development Team member, wants to know how long a Daily Scrum is. What's the timebox for a Daily Scrum?
SMC 문제 25
To ensure that there is no gap between the customer's expectation from the project, and the deliverables produced, the Scrum Master has to eliminate environmental obstructions that the team may face, that may affect the quality of the deliverables. To do so, apart from Quality Planning, the team has to ensure Quality Control, and Quality Assurance. Which of the following statements is true regarding Quality Assurance and Quality Control?