PMP-KR 문제 481
The other options are not correct because they do not match the description of the team lead. Directive leadership is a style of leadership that involves giving clear and specific instructions to the followers and expecting them to follow them without question2. Commanding leadership is a style of leadership that involves exerting control and authority over the followers and demanding compliance and obedience3. Servant leadership is a style of leadership that involves putting the needs and interests of the followers first and empowering them to grow and develop4. None of these styles reflect the team lead's behavior of being highly engaged and involved in the project and operating without a chain of command or authority levels. References: 1 5 Principles to Guide Adaptive Leadership, Harvard Business Review2 Directive Leadership Style: Definition, Examples, Pros & Cons, Indeed3 Commanding Leadership Style: Definition, Examples, Pros & Cons, Indeed4 Transformational versus Servant Leadership: A Difference in Leader Focus, Regent University.
PMP-KR 문제 482
PMP-KR 문제 483
Explaining the situation to stakeholders (A) may be needed, but doing it first without facts risks misinformation and loss of credibility. Seeking sponsor guidance (B) can help with authority and escalation, but it should be informed by a clear understanding of issues and options. "Arrange a time to meet with the team" (C) is essentially the same intent but less direct; the immediate action is to meet and diagnose. A fact- based understanding enables a recovery plan, including tighter change control and realistic rebaselining if required.
PMP-KR 문제 484
프로젝트 관리자는 무엇을 해야 할까요?
Therefore, the best action is to review and update the communications management plan. This allows the project manager to improve reporting frequency, communication channels, dependency tracking, escalation paths, and stakeholder visibility in a structured and sustainable way. Option C may help temporarily, but it does not correct the underlying communication framework. Options A and D escalate too early before the project manager has used the proper project management process to address the concern. PMP logic generally favors fixing the process before escalating. Updating the communications plan is the strongest answer because it directly addresses the stakeholder complaint and improves coordination across the project in an organized, repeatable manner.
PMP-KR 문제 485
어떤 기술이 프로젝트 관리자가 성과물을 빨리 완성하는 데 도움이 될까요?
* It reduces the risk of rework and waste by allowing the project manager to adjust the plan as more information becomes available or as the requirements change.
* It increases the flexibility and responsiveness of the project team by allowing them to focus on the most important and urgent tasks in each iteration, rather than following a rigid and detailed plan.
* It improves the quality and customer satisfaction of the deliverable by allowing the project manager to incorporate feedback and lessons learned from each iteration into the next one, and by delivering incremental value to the customer.
* It enhances the collaboration and communication among the project team and stakeholders by involving them in the planning and execution of each iteration, and by providing frequent and transparent updates on the project progress and status.
The other options are not the best techniques to accelerate the deliverable in this scenario. Impact mapping (A) is a strategic planning technique that helps the project manager to align the project deliverables with the organizational goals and the customer needs, by identifying the actors, impacts, and deliverables involved45.
However, impact mapping does not address the issue of how to plan and execute the project in a fast and adaptive way, especially when the project has failed to comply with a product functionality. Collective code ownership is a software development practice that encourages the entire team to share the responsibility and the authority to modify any code file as necessary, to improve the quality, the performance, and the functionality of the software product67. However, collective code ownership does not address the issue of how to plan and execute the project in a fast and adaptive way, especially when the project has a predominantly predictive approach. Scrum of Scrums (D) is a scaling technique that helps multiple Scrum teams to coordinate and collaborate on complex and interdependent projects, by having representatives from each team meet regularly to report on their progress, their impediments, and their dependencies89. However, Scrum of Scrums does not address the issue of how to plan and execute the project in a fast and adaptive way, especially when the project has a predominantly predictive approach. References: https://www.teamgantt.com
/waterfall-agile-guide/hybrid-approach
https://www.float.com/resources/hybrid-project-management/
https://en.wikipedia.org/wiki/Rolling-wave_planning
- 다른 버전
- 1135PMI.PMP-KR.v2026-08-27.q1110
- 5358PMI.PMP-KR.v2026-08-21.q86
- 1534PMI.PMP-KR.v2026-08-21.q927
- 6537PMI.PMP-KR.v2026-05-07.q925
- 1771PMI.PMP-KR.v2026-03-28.q242
- 5182PMI.PMP-KR.v2026-03-27.q939
- 5857PMI.PMP-KR.v2026-03-09.q911
- 5560PMI.PMP-KR.v2026-03-07.q681
- 6157PMI.PMP-KR.v2026-03-05.q857
- 3382PMI.PMP-KR.v2026-03-04.q280
- 5892PMI.PMP-KR.v2025-03-29.q751
- 5710PMI.PMP-KR.v2024-02-27.q469
- 1689PMI.PMP-KR.v2024-02-10.q164
- 3782PMI.PMP-KR.v2023-12-04.q235
- 1610PMI.PMP-KR.v2023-10-19.q177
- 2671PMI.PMP-KR.v2023-05-15.q244
- 최근 업로드
- 121ServSafe.ServSafe-Manager.v2026-09-10.q34
- 123Salesforce.Slack-Dev-201.v2026-09-10.q81
- 123Microsoft.DP-600.v2026-09-10.q105
- 165IAPP.CIPT.v2026-09-10.q179
- 188Cisco.500-420.v2026-09-09.q50
- 183WGU.Introduction-to-IT.v2026-09-09.q52
- 238GARP.2016-FRR.v2026-09-08.q268
- 147Oracle.1Z0-1051-26.v2026-09-08.q15
- 168DAMA.MD-1220.v2026-09-08.q48
- 150Saviynt.SCAIP.v2026-09-07.q20
PDF 파일 다운로드
메일 주소를 입력하시고 다운로드 하세요. PMI.PMP-KR.v2026-06-01.q1069 모의시험 시험자료를 다운 받으세요.