PSM-I 문제 21

What does it mean for a Development Team to be cross-functional?

PSM-I 문제 22

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

PSM-I 문제 23

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to
resolve only a small portion of the impediments. Which three techniques would be most helpful in this
situation? (Choose three.)

PSM-I 문제 24

Who should make sure everyone on the Development Team does his or her tasks for the Sprint?

PSM-I 문제 25

A Sprint Retrospective should be held: