PSM-I 문제 51
Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose the best two answers.)
PSM-I 문제 52
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
A good way to continue is:
PSM-I 문제 53
What is the recommended size for a Scrum Team? (Choose the best answer.)
PSM-I 문제 54
Which are properties of the Daily Scrum? (Choose two.)
PSM-I 문제 55
When do Development Team members take ownership of a Sprint Backlog item?