PRINCE2-Foundation 문제 276
How many tasks does the product-based planning technique describe?
PRINCE2-Foundation 문제 277
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
PRINCE2-Foundation 문제 278
Which describes a risk event?
PRINCE2-Foundation 문제 279
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
PRINCE2-Foundation 문제 280
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?