문제 1

You want to perform an SAP S/4HANA conversion using SUM with DMO. Which steps run before the beginning of the technical downtime, independent of your SUM configuration?
There are 3 correct answers to this question.
Response:

문제 2

You are planning an SAP S/4HANA conversion. Which conversion-specific tasks need to be performed during the preparation phase?
There are 2 correct answers to this question.
Response:

문제 3

You are running an SAP ECC system. For which of the following activities does SUM allow you to use the Near Zero Downtime Maintenance (NZDM) capabilities?
There are 3 correct answers to this question.
Response:

문제 4

You downloaded content from the SAP note 1000009 ("ASU Toolbox 2008"). Which transaction needs to be executed to use that content in the ASU Toolbox?
Please choose the correct answer.
Response:

문제 5

You are performing an upgrade of an SAP ECC development system with SUM. What is the earliest point when the upgrade is considered complete and you can allow all dialog users to log on to the system?
Please choose the correct answer.
Response: