Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
Cost & Budget
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.