Project structure.
You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

문제 2

You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?

문제 3

You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

문제 4

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling.
What do you recommend for milestone definition?

문제 5

How can you update the degree of processing for an activity?