PMI-SP 무료 덤프문제 온라인 액세스
| 시험코드: | PMI-SP |
| 시험이름: | PMI Scheduling Professional |
| 인증사: | PMI |
| 무료 덤프 문항수: | 326 |
| 업로드 날짜: | 2025-12-12 |
CORRECT TEXT
Fill in the blank with the appropriate word. When activities are logically linked, they become the .
Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this project, though he is supposed to be at his second milestone, which accounts for half of the project completion. There have been some errors in the project, which have caused Allen to spend $2,093,754. What is this project's schedule variance?
Della works as a Project Manager for BlueWell Inc. A number of projects are running under her guidance. You, being a team leader of a project, provide Della the performance indexes of your project. The schedule variance (SV) of your project is zero. What does this figure depict?
John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.