A project is chartered to implement an artificial-intelligence solution that will automate repetitive tasks. The risk manager conducts a comprehensive risk study and identifies a high risk of system slowness, which could cause delays in generating and circulating reports among different stakeholders.
What should the risk manager do?
During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.
What should the risk manager do to address the new risk of increased logistics costs?
The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.
What should be the risk manager ' s next step?