문제 1

A project is to be started with a team of nine existing and nine new members. The scrum master feels that the team is too large and wants to break it into three teams. The scrum master sets aconstraint that each team have an equal number of existing team members for knowledge sharing and experience.
What should the scrum master do to accomplish this?

문제 2

A project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?" How should the agile lead respond?

문제 3

To create the project vision, an agile team has scheduled an initial meeting with their customer representative.
What should the team bring to this meeting?

문제 4

The team is aware that they will need to integrate a new component to their solution in the next few weeks.
The team does not have any experience with this component.
What should the team do next?

문제 5

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the Scrum Master do?