Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where
actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
A Production operator in your company is required to report production activities, such as completing or
scrapping production units, by referencing a work definition without creating work orders.
Identify the manufacturing transaction that a production operator can perform for reporting such activities.
An order entry specialist creates a Back-to-Back order for product item with an intention of fulfilling by
in-house manufacturing. The fulfillment line is scheduled and Supply Chain Orchestration (SCO) has initiated
creation of a Supply Order rather than Work Order.
Identify two options that can cause this situation.
Your Customer has implemented Oracle Cloud Manufacturing and the Manufacturing user is in the process of
defining Work Definition and Operations. However, this user is unable to assign an ad hoc item, Grease, to an
operation.
Identify the reason.