When implementing Project Performance Reporting, your customer has the following requirements:
* Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
* As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
Your customer wants additional project information for detailed account balance maintenance, reconciliation, and reporting. Identify the configuration in subledger accounting that can be set up to fulfill this requirement.
(Choose the best answer.)
Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)