For a new AHV cluster installation, a customer has 20 NX-8155-G6 nodes with quad port SFP NICs.
The customer wants to meet the following guidelines:
* Take advantage of all available 10GbE links
* Achieve maximum throughput per VM
* Use of redundant ToR switches
* Fastest reconvergence during link failure
How should the load balancing be configured on the host?
In a 20-node ESXi deployment, the customer needs additional resiliency to survive the loss of two nodes concurrently.
Which configuration should the consultant use to ensure that the appropriate resources are available?
Refer to the exhibit.
A consultant is installing AOS 5.10 and ESXi 6.5 on three nodes. During the Foundation process, ESXi 6.5 is not available as one of the choices for hypervisor.
Which solution should the consultant use?
A consultant is onsite with a customer running Foundation VM (FVM) and discovers that there is no connectivity between the FVM and their laptop. The consultant verifies the following:
* The consultant's laptop and Nutanix nodes are plugged into a flat switch.
* The laptop, switch and nodes are plugged into supported power supplies.
* The laptop network adapters and FVM are configured with their corresponding IP addresses.
What is the cause for the connectivity failure to the FVM?
A consultant deploys a four-node VMware ESXi cluster and vCenter server. An HA/DRS cluster is configured for all four nodes. The customer deploys five new VMs on the cluster.
During the knowledge Transfer, a network cable on one node is removed to demonstrate HA and migration of the VMs to another host. In the HA/DRS cluster settings, the VM Restart Priority for all CVMs is set to Disabled. The customer observes warnings that the CVM on the ejected host is no longer powered on.
Which ESXi HA/DRS cluster setting is missing?