문제 1

Your organization uses Project Server 2013. Your environment's default task mode is auto scheduled. Your environment allows manually scheduled tasks to be displayed in Project Web App (PWA).
You create a detailed enterprise project with resources assigned to auto scheduled tasks. Your project has three phases, but only the first two phases have been approved to begin work.
You need to ensure resources cannot provide status on phase three assignments.
What should you do?

문제 2

You work as a project manager in an organization that uses Project Server 2013. All project managers belong to the Project Management Office (PMO) and use Project Professional 2013.
A member of the PMO is responsible for initiating a new project schedule in Project Server and fills in critical project-level fields such as Sponsor and Project Budget. The PMO publishes the new project and then, through email, instructs the project manager to complete a detailed schedule.
You are responsible for planning and managing the schedule, including approving task updates from team members. After speaking to your team members, you discover that task updates have been submitted, but you are not receiving them; instead, these updates are going to the person in the PMO who initially set up the schedule.
You need to solve this problem. What should you do?

문제 3

An organization has performed a portfolio analysis in Project Server 2013 by defining a list of drivers and establishing the prioritization for next year's portfolio.
You are finalizing the second quarter for the next year, which is when changes to the strategy will take place. For transparency reasons, the organization intends to keep historic analysis for a certain number of years.
You need to reevaluate your portfolio for the rest of the year, considering new projects and current executing projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

문제 4

You are a program manager in the Project Management Office (PMO) of an organization that has Project Server 2013.
You plan to have a weekly project meeting review with all the project managers, and one of the topics that you will cover is the status of all active Issues.
Your need to create a report that displays the following information:
- Name, Status, Priority, and Resolution of all Issues
- Name, Owner, and Start and Finish date of all projects
What should you do?

문제 5

You are an area project manager who uses Project Server 2013.
You are aligning and planning your team's availability against existing and proposed projects.
You need to estimate your team members' work load for future time periods against projects that have not completed a work breakdown structure (WBS) yet. You need to account for both existing and planned projects.
What should you do?