You are a program manager in an organization that uses Project Server 2013. The allow master projects to be saved and published function is not enabled.
Your program contains seven active projects managed in Project Online.
You need a way to review the tasks flagged as milestones in all seven active projects at one time.
You open Project Center in Project Web App (PWA).
What should you do next?
You are a portfolio manager at an organization that uses Project Server 2013.
You supervise five very large projects. Each project has its own project manager and a project team with many resources. One of your main activities is reviewing all documentation of the five projects. The project teams are constantly updating and publishing new documents in the Project Site of each project.
You need to implement an information review process that meets the following requirements:
- Receive a notification every time a document is updated or published in the Project
Sites.
- Have a centralized way to view the notifications.
- Implement the process in the least amount of time.
What should you do?
You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using Project Professional 2013.
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?
You are a portfolio manager for an organization that uses Project Server 2013.
You plan to create several portfolio reports for the executive team.
You need to ensure that your first report shows a list of all projects in your organization with
timephased information regarding how the Actual Work and the Actual Cost have varied on
a monthly basis.
What should you do?
You are a program manager for a company that uses Project Server 2013 and Project Professional 2013. You manage the implementation of a data warehouse.
You have set up your program master project with subprojects for each implementation area.
You need to make edits to the dependencies between projects.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)