You are a program manager for an organization that uses Project Server 2013.
You work in a master project, which contains ten sub-projects. One of your project managers makes changes to a sub-project and publishes it.
You open the master project and realize that these changes are not reflected in the master project schedule.
You need to ensure these changes are reflected in the master project.
What should you do?
Your organization is performing a Portfolio Analysis in Project Server 2013.
You want to create a consolidated Portfolio Analysis optimization based on Cost and Resource data, which will be part of the project information in Project Server 2013.
You plan to provide different simulations to your organization by using those parameters and returning the best prioritization.
This organization has two different unit directors, who have the final decision on the consolidated Portfolio Analysis results.
You need to provide the ability for your unit directors to modify the final portfolio selection.
Which element should you use?
You are a project manager for an organization that uses Project Server 2013. Synchronization is enabled. Project Sites at your organization are created by a default template when a new schedule is published.
You are the Project Owner of a schedule. You have a Project Site associated with this schedule.
You need to quickly change the look and colors of your schedule's Project Site.
What should you do?
DRAG DROP
You work as a team member for an organization that uses Project Server 2013.
The organization tracks work in hours and has single-entry mode enabled. You are required to complete a timesheet at the end of each week. For this week's timesheet, you only have one assigned task to complete.
You need to ensure that your timesheet is accurate and ready for approval.
Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)
You are a program manager for a company that uses Project Server 2013 and Project Professional 2013. You manage the implementation of a data warehouse.
You have set up your program master project with subprojects for each implementation area.
You need to make edits to the dependencies between projects.
What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)