문제 1

You develop a solution that is managed in Microsoft Visual Studio Team Foundation Server (TFS) source control using three branches according the following table.

The branch hierarchy is shown in the exhibit. (Click the Exhibit button.)

A new project requires you to divide your team into two separate, and largely independent, teams named Feature Team 1 and Feature Team 2. Each team works on different features.
You need to recommend an effective long-term strategy that:
Allows parallel development,
Allows independent feature releases,
Minimizes conflicts,
Supports integration, and
Allows bug fixes to production code.
What should you do?

문제 2

You are the lead developer and architect of a development team that develops line of business (LOB) applications.
You need to define an architectural design process for the LOB applications.
Which three architectural goals and principles should you adopt? (Each correct answer presents a complete solution. Choose three.)

문제 3

DRAG DROP
You are developing a new application that contains complicated validation and transformation logic on data pulled from three separate source systems.
You need to get feedback from your stakeholders to verify that your application meets their requirements before any other development tasks have been started. You also need to ensure that this application sub-system is correct before any other dependent module can be developed.
What should you do? (To answer, move the five appropriate actions from the list of actions to the answer area and arrange them in the correct order.)

문제 4

Your company is developing a web application by using the Microsoft Visual Studio Scrum
2.0 process template. The development team committed to deliver a set of Product Backlog Item (PBI) work items for the upcoming sprint.
You implement the initial tests for the PBIs in scope for the upcoming sprint. You plan to add more tests during the sprint.
You need to ensure that your test plan automatically includes any new tests.
What should you do?

문제 5

---
You manage a development team for a group of stakeholders that are physically remote from your development center. Stakeholders have blocked out dates and times on their schedules for your team.
The stakeholders are concerned that several of the project requirements will not meet their needs due to changing market conditions.
You need to ensure that the following requirements are met: s
Your team is doing effective and efficient work.
The work is meeting the needs of the business.
The project's timeline is not at risk.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)