70-348 무료 덤프문제 온라인 액세스

시험코드:70-348
시험이름:Managing Projects and Portfolios with Microsoft PPM
인증사:Microsoft
무료 덤프 문항수:48
업로드 날짜:2026-07-14
평점
100%

문제 1

You are a project manager for an organization that is using Microsoft Project.
You have enabled Single Entry Mode and team members update their task using timesheets.
You need to see how these updates impact your project before you approve the tasks.
What should you do?

문제 2

You are a project manager for an organization that uses Microsoft PPM. You plan each project in phases.
Team members must only see the assignments from a selected phase. All reports and project schedule views must reflect the entire project schedule, so the entire project is visible to the management team.
You need to configure Microsoft PPM.
What should you do?

문제 3

Your organization is using Microsoft PPM to manage and track all projects.
The Project Management Office (PMO) needs to know which of the projects are aligned to the organization's strategic objectives.
You need to configure Microsoft PPM to use Portfolio Analysis.
Which two activities should you perform? Each correct answer presents part of the solution.

문제 4

DRAG DROP
You are a project manager in an organization that is using Microsoft PPM for work management.
You have already accepted all status updates in the Approval Center, but you are still unable to see the updates in your project schedule.
You need to ensure that status updates are reflected in your project schedule.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

문제 5

You are a portfolio manager for an organization that uses Microsoft PPM to manage projects. You plan to implement Power BI.
You need to import into Power BI by using the Microsoft Project Online content pack.
What should you do?

댓글 추가

귀하의 메일주소는 공개되지 않습니다. 필수 입력 사항은 표시되어 있습니다. *

insert code
그림의 인증번호를 입력하세요.