You have an unscheduled, unassigned task in your Project Professional 2010 schedule. You identify an available resource. You need to assign the task to the resource without scheduling the task. What should you do?
You use Project Professional 2010 to manage a project. John, a team member, is over-allocated. You need to identify the dates on which the over-allocation occurs. What should you do?
In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:
-Tasks that are not started.
-Tasks in progress.
-Tasks that have finished.
-Total remaining effort for each group of tasks.
What should you do on the View tab?
All tasks in your project use the Auto Schedule mode. Several tasks are in progress. You need to reschedule all the remaining work on the project. You also need to achieve this goal without having rigid constraints set to your project's tasks. What should you do?