You are a project manager who uses Project Standard 2013.
A colleague sends you a Microsoft Excel file that contains a list of tasks that define a project you must complete.
You need to create a project file that contains this task list, ensuring that any fields are mapped correctly.
What should you do?
You manage a project schedule by using Project Professional 2013.
You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00.
You need to view graphically which tasks and resources are causing the $5,000.00 cost variance.
What should you do?
DRAG DROP
You are an independent project manager who uses Project Professional 2013 and wants to extend the standard functionalities of it.
You need to find and install an app from the Office Store.
Which four actions should you perform in sequence? (To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.)
You are a project manager who uses Project Standard 2013.
You work on a project that requires you to generate many documents. Each task in your project plan must have a document associated and stored in your Microsoft SharePoint Intranet Environment. These documents are 25 megabytes in size.
You need to share this project plan by email with your team and ensure that they can easily access the documents.
What should you do?
You are a program manager for a complex software development project. You use Project Professional 2013 to manage your project. Your resources work on many different projects across the program, and you need to resolve resource over allocations. Your project team uses a resource pool to manage resources.
Resource1 has been assigned to assist on a project that is on the critical path. After assigning Resource2 to the task, you notice that Resource1 is over allocated during the month of November. Project A, which is on critical path, takes priority over Project B, which Resource1 is also assigned to.
Using resource leveling in Project Professional 2013, you need to resolve the over allocation for Resource1 for the month of November only.
What should you do?