You are a project manager for an organization that uses Microsoft PPM to manage project resources. You are responsible for several projects.
Your organization is trying to improve the resource management maturity level, and has just finished the training on the new process for all project and resource managers.
Resource requests must be submitted based on units less than or equal to 75 percent, leaving 25 percent of the resources' capacity for administrative work.
You need to enter the resource requests.
What should you do?
You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.
You have the following requirements:
You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.
Where should you add resources?
You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description, Proposed Cost,
Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should use? Each correct answer presents part of the solution.
DRAG DROP
You are the Microsoft PPM administrator for a large organization.
You need to ensure that line managers can delegate timesheet approvals to their team members.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
You are the administrator for an organization that uses Microsoft PPM. The IT department has 10 developers. You assign all developers to a team named Developers. The IT manager plans to use the team feature of Microsoft PPM.
You need to ensure that all project managers can use Team assign instead of Resource assign.
What should you do to finish the Developers team configuration?