070-178 무료 덤프문제 온라인 액세스

시험코드:070-178
시험이름:Microsoft Project 2010, Managing Projects
인증사:Microsoft
무료 덤프 문항수:70
업로드 날짜:2026-08-26
평점
100%

문제 1

Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within the project. What should you do?

문제 2

You have a Project 2010 schedule that contains the following tasks: Inactive tasks Manually scheduled tasks Manually scheduled summary tasks Tasks that contain strikethrough font You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?

문제 3

You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?

문제 4

Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today's data. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

문제 5

You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?

댓글 추가

귀하의 메일주소는 공개되지 않습니다. 필수 입력 사항은 표시되어 있습니다. *

insert code
그림의 인증번호를 입력하세요.