Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within the project. What should you do?
You have a Project 2010 schedule that contains the following tasks: Inactive tasks Manually scheduled tasks Manually scheduled summary tasks Tasks that contain strikethrough font You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?
You need to select a view that allows you to use the drag-and-drop feature on the resource assignments and unassigned tasks. What should you do?
Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today's data. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)