테스트 관리자가 프로젝트에 대한 위험 평가를 수행합니다. 식별된 위험 중 하나는 다음과 같습니다. 하청업체가 약속을 이행하지 못할 수 있습니다. 이 위험이 실현되면 현재 주기에 필요한 테스트 완료가 지연됩니다.
다음 문장 중 어느 것이 위험을 올바르게 설명하고 있습니까?
정답: D
A product risk is a risk that affects the quality or timeliness of the software product being developed or tested1. Product risks are related to the requirements, design, implementation, verification, and maintenance of the software product2.
The risk of the sub-contractor failing to meet his commitment is a product risk, as it could cause a delay in the completion of the testing required for the current cycle, which in turn could affect the release date of the product. The release date is an important aspect of the product quality, as it reflects the customer satisfaction and the market competitiveness of the product3.
The other options are not correct because:
A . It is not true that any risk associated with development timeline is a product risk. Some risks could be project risks, which are risks that affect the management or control of the software project, such as budget, resources, schedule, or communication1. For example, a risk of losing a key project stakeholder is a project risk, not a product risk.
B . It is not true that the risk is no longer a risk for the Test Manager since an independent party is managing it. The Test Manager is still responsible for ensuring that the testing activities are completed according to the test plan and the quality objectives4. The Test Manager should monitor and control the sub-contractor's performance and communicate with him regularly to identify and mitigate any potential issues or deviations5.
C . It is not clear what is meant by "object" in this option, but it could be interpreted as the software system under test or the test object6. In any case, the risk is not an object risk, as it does not affect the successful completion of the object, but rather the successful completion of the testing of the object. An object risk could be a risk that affects the functionality, reliability, usability, efficiency, maintainability, or portability of the software system under test2. For example, a risk of the software system having a high complexity or a low testability is an object risk, not a product risk.
Reference =
1 ISTQBCertified Tester Foundation Level Syllabus v4.0, 2023, p. 97
2 ISTQBCertified Tester Foundation Level Syllabus v4.0, 2023, p. 98
3 ISTQBCertified Tester Foundation Level Syllabus v4.0, 2023, p. 99
4 ISTQBCertified Tester Foundation Level Syllabus v4.0, 2023, p. 100
5 ISTQBCertified Tester Foundation Level Syllabus v4.0, 2023, p. 101
6 ISTQBCertified Tester Foundation Level Syllabus v4.0, 2023, p. 102