A software manufacturer is planning to convert their VDC to IaaS. As part of the transformation to IaaS the company realizes they have to make several organizational changes.
Which is the most likely starting point for their organizational transformation?
A small organization plans to migrate a critical application from a traditional, physical infrastructure to the first servers in their VDC. This will be one of several applications the organization plans to migrate over the next 2-3 years.
As this is a new VDC implementation, they have not yet realized any of the benefits of a fully virtualized infrastructure. They have retained an experienced consulting service to help them build a detailed migration plan.
Which migration strategy will they most likely use and why?