PK0-400 문제 11
Which of the following documents does a vendor rely on to commit funding and resources to a project?
PK0-400 문제 12
A project manager is creating the WBS.
In which of the following phases is the project?
In which of the following phases is the project?
PK0-400 문제 13
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?
Which of the following documents should the project manager create?
PK0-400 문제 14
Which of the following is a key aspect of the Agile project management methodology?
PK0-400 문제 15
A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.
Which of the following conflict resolution techniques is the project manager using?
Which of the following conflict resolution techniques is the project manager using?