PK0-004 문제 356

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?

PK0-004 문제 357

A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
Project description
Draft project timeline and schedule
Rough milestones
Draft project budget
Draft resources required
High-level risk review
Which of the following sections should be included in this document?

PK0-004 문제 358

A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

PK0-004 문제 359

Which of the following is the primary purpose of an MOA or an MOU?

PK0-004 문제 360

A project team is brainstorming and documenting what might go wrong in a project, the possible impact, and potential actions should certain situations arise.
Which of the following contains actions the team is MOST likely to consider?