C-TS422-1909 문제 51

A material has been set up as a phantom assembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?

C-TS422-1909 문제 52

What are attributes of the SAP S/4HANA Simplification list?
There are 3 correct answers to this question.
Response:

C-TS422-1909 문제 53

How can you enhance the system statuses of a production order scenario with user statuses?
Please choose the correct answer.
Response:

C-TS422-1909 문제 54

Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?

C-TS422-1909 문제 55

Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?