A. When a team is created to deliver a specific product
B. When delivering an ongoing service to a customer
C. When simple requests to update a product are implemented
D. When an established team performs product maintenance
A. It requires a specific dedicated project manager
B. It is executed by program management
C. It is delivered by a temporary team
D. It is delivered by an established team