CTFL_001 문제 51

Testing should be stopped when:

CTFL_001 문제 52

사용자가 발견한 오류의 원인은..?

CTFL_001 문제 53

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document b. The overall estimated costs, timescales and resource requirements c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit

CTFL_001 문제 54

다음 중 운영 체제의 유지 관리 테스트를 위한 세 가지 트리거 중 하나를 나타내지 않는 것은 무엇입니까?

CTFL_001 문제 55

"얼마나 많은 테스트로 충분합니까?"